Project Description

Client: Tamesis Joint Venture. Part of a £190million project to help clean up the River Thames

Construction work started spring 2012 and is scheduled for completion 2014 at Beckton, the largest sewage treatment works in Europe.

Requirements: Design, manufacture and installation of a Wash Water Booster Set providing final effluent water to process equipment.

Fulfillment: 4 x 75kW pumps, 2 x BOLL self cleaning filters, 2 x bespoke 1000 litres expansion vessels and two bespoke kiosks to house the booster set with filters and a Form 4 control panel